KIV commenced the commissioning a new gasification EfW CHP and district heating scheme in September 2008. The plant has been designed to environmental standards above and beyond the EU Waste Incineration Directive (WID), which also incorporates Best Available Technique (BAT), lodged with the EU BREF documents office. The plant will be an EU ‘showcase’ project, which incorporates a presentation room for coach parties of visitors.
Approximately five years ago, KIV commenced a joint development for the gasification EfW CHP plant with Celje town council. The plant has an 18MWth input capacity for <38,000 tpa of a mixed fuel (80% RDF + 20% Sewage Sludge), with an average CV of 13.6MJ/kg, based on a guaranteed 8,000 hrs/annum availability. The scheme is connected to an existing District Heating scheme, which has a 110oC flow temperature. The scheme is ‘heat led’ and therefore produces a reduced amount of gross power at 2.1 MWe. If the scheme was ‘electricity led’, it would produce 3.8MWe of gross power.